Question

Daniels failure to deliver ice-cream makers and waffle makers on time resulted in a two-week delay in the opening of Sheenas new ice-cream parlor. Sheena incurred a heavy loss since she had to pay the rent for those two weeks as well as salaries to the personnel hired. In this case, which of the following remedies is a court most likely to award Sheena?

A. liquidated damages

B. consequential damages

C. nominal damages

D. specific performance

E. differential damages

Answer