Question

Consider the MPS, BOM, and inventory data shown.

Master Production Schedule:

The following table shows the MPS start quantities for the next 10 weeks.


Finished Item A 1 2 3 4 5 6 7 8 9 10











Finished Item A MPS Start 20
40 30
20
40


Bill of Material:

- Item A uses 2 each of component D, 1 each of component C and 2 each of subassembly B.

- Subassembly B uses 2 each of component E.

Selected Inventory Data:


Item Lot Sizing Rule Lead Time Scheduled Receipts On-Hand
B L4L 1 40 in period 1
C POQ = 3 2
40
D FOQ = 250 1
100
E L4L 2 160 in period 2

Construct the MRP schedule using the preceding information.

Answer

This answer is hidden. It contains 139 characters.