Question

Calculate the latest start for Task D if one of its successors, Task F, has a latest start on day 9, its other successor, Task E, has a latest start on day 10, and the duration of Task D is 2 days.
a. day 8
b. day 7
c. day 12
d. Cannot be calculated based upon information given.

Answer

This answer is hidden. It contains 1 characters.