Question

Calculate the latest finish for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has a latest start of day 7, and the duration of Task B is 2 days.
a. day 5
b. day 3
c. day 7
d. Cannot be calculated based upon information given.