Question

Calculate the forecasted cost at completion if the total budgeted cost = $10,000, the CEV is $8,000, and the CAC is $4,000.
a. FCAC = $5,000
b. FCAC = $20,000
c. FCAC = $6,000
d. FCAC = $4,000

Answer

This answer is hidden. It contains 1 characters.