Question

Calculate the forecasted cost at completion if the cumulative actual cost is $10,000 and the re-estimate of remaining work to be performed is $5,000.
a. FCAC = $5,000
b. FCAC = $15,000
c. FCAC = 2
d. FCAC = 0.5