Calculate the earliest finish for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor, Task C, finishes on day 4, and the duration of Task D is 2 days.
a. day 6
b. day 3
c. day 4
d. Cannot be calculated based upon information given.