Question

Calculate the earliest finish for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days.
a. day 5
b. day 3
c. day 1
d. Cannot be calculated based upon information given.

Answer

This answer is hidden. It contains 1 characters.