Question

Below is the information pertaining to five jobs in process on October 22. Determine the sequencing of these five jobs at this machine using the critical ratio rule. Assume a seven-day workweek.
Job Remaining Arrival Date Due Date
Processing Time
A 2 days Oct. 12 Oct. 29
B 6 days Oct. 15 Oct. 28
C 5 days Oct. 18 Oct. 30
D 10 days Oct. 1 Oct. 31
E 8 days Oct. 10 Oct. 27

A. A-C-B-E-D
B. E-B-A-C-D
C. B-E-C-D-A
D. B-C-E-A-D

Answer

This answer is hidden. It contains 115 characters.