Question

Barry's Software Development Team

Barry was assigned recently to a large team working on a major software release that was taking longer than expected. Barry and the other latecomers into the project spent a month partnered with a senior programmer who went over the project in detail with them and got them up to speed. Unfortunately, this training put the project even farther behind schedule. After a few months of working on the project with so many other programmers, Barry's work output becomes noticeably lower than it was before when he was working independently.

Barry's reduced work output is most likely due to:

A. a lack of knowledge.

B. job dissatisfaction.

C. a hostile work environment.

D. social loafing.

E. lack of proper supervision.

Answer

This answer is hidden. It contains 116 characters.