Question

At the beginning of the project, it may not be possible to estimate the costs for all activities with a level of confidence regarding their accuracy. This is especially true for
a. projects with a short term.
b. longer-term projects.
c. projects that are similar to ones completed by the organization before.
d. projects with activities that are serially related.

Answer

This answer is hidden. It contains 1 characters.