Question

Assume that activity G has the following times:

Early start time = 7 days

Early finish time = 13 days

Late start time = 15 days

Late finish time = 21 days

Which of the following statements is true about activity G?

A) Activity G takes 14 days to complete.

B) Activity G has a slack time of 8 days.

C) Activity G is on the critical path.

D) Activity G takes 2 days to complete.