Question

Alpha Commodities, Inc., agrees to deliver ten tons of sheet metal to Beta Builders Corporation. The agreement states that delivery is to be within "3" days, although the parties intend "30" days. Alpha cannot convince Beta to amend the contract. Alpha should seek
a. damages.
b. reformation.
c. rescission.
d. specific performance.

Answer

This answer is hidden. It contains 1 characters.