Actual costs and quantities:
Direct materials used 38,000 feet @ $6.20 per foot
Direct labor hours used 50,660 hours
Direct labor rate per hour $16
Factory overhead $211,600
25,000 units were produced during the period.
Standard costs and quantities per unit:
Direct materials 5 ft. @ $6.10 per ft.
Direct labor 2 hours @ $17 per hour

Factory overhead (based on budgeted production of 24,500 units)

Answer

This answer is hidden. It contains 71 characters.