Ace Contractors, Inc., agrees to build a motel for Best Motels Corporation. The project proceeds according to plan, but before it is done, Best tells Ace to quit. Ace may recover
a. the contract price less costs of materials and labor.
b. the contract price.
c. the costs needed to complete construction.
d. profits plus the costs incurred up to the time of the breach.