Question

A standard work year is 2,080 hours at the Luther Mill and it takes about 2 hours to fill a customer order. The manager at the mill is always concerned about employee idle time, so he aims for a capacity cushion of two percent. Last year saw 15,000 customer orders at the mill and the manager has a new Mercedes in mind as a company car, so he hopes that there is an increase of 10% in customer orders for next year. How many workers will the manager need to have at the mill next year?

A) 10

B) 13

C) 16

D) 19

Answer

This answer is hidden. It contains 116 characters.