Question

A project has three paths. A-B-C has a length of 25 days. A-D-C has a length of 15 days. Finally, A-E-C has a length of 20 days. Which one of the following statements is true?

A) A-D-C is the critical path.

B) A-B-C has the most slack.

C) The expected duration of this project is 25 days.

D) The expected duration of this project is 25 + 15 + 20 = 60 days.

Answer

This answer is hidden. It contains 43 characters.