A preliminary when the contractor has completed the initial conceptual specifications, drawings, or
flowcharts. The purpose of this preliminary design review meeting is to get the customer's agreement.
a. project status review meetings
b. problem-solving meetings
c. design review meetings
d. post-project evaluation meetings