A-Plus Properties, Inc., and Best Construction Company sign a contract that specifies the amount to be paid. Additional compensation may be justified by
a. changes in the market value of the project during the contract.
b. extraordinary difficulties unforeseen at the time of the contract.
c. no circumstances.
d. ordinary business risks that occur after the time of the contract.