Question

A monthly production schedule calls for 20,000 units of product A, 10,000 units of product B, and 5,000 units of product C. If there are 20 days of production available each month, what is the appropriate uniform load per day?
A. 20,000 units of A; 10,000 B; 5,000 C.
B. 1,750 units each of A, B, and C.
C. 1,000 units of A; 500 B; 250 C.
D. There is not enough information given to calculate the answer.