Question

A manager is interested in using linear programming to analyze production for the ensuing week. She knows that it will take exactly 1.5 hours to run a batch of product A and that this batch will consume two tons of sugar. This is an example of the linear programming assumption of:

A) linearity.

B) certainty.

C) continuous variables.

D) whole numbers.