Question

A machine center can produce 175 units per day at 100% utilization. Demand is 75 units per day, and suppliers are capable of delivering raw materials to support production of 125 units per day. If demand doubles, the flow rate will be
A. 100 units.
B. 125 units.
C. 150 units.
D. 175 units.