Question

The risk-free rate is 5%, the market risk premium is 8% and the project's beta is 1.25. Calculate the certainty equivalent cash flow for
year-3.
A. $228.35
B. $197.25
C. $300
D. None of the above

Answer

This answer is hidden. It contains 59 characters.