Question

Evaluating a functional manager's performance relative to budgets can be an effective control when
A) the process used in developing budgets is open and participative.
B) the process reflects the economic best-case scenario developed by the functional manager.
C) the process reflects the economic worst-case scenario developed by the functional manager.
D) the process relies solely on quantitative criteria to evaluate the functional manager's performance.