Question

Bill has been working his plan for about three months. He is now discussing his progress with Jim, his supervisor. If Bill and Jim are using the MBO planning process, this discussion is called ________.

A) performance feedback

B) redirection of goals

C) advise and adjust

D) the milestone checkpoint