Question

A ________ is bar graph with time on the horizontal axis and activities to be scheduled on the vertical axis.
A) graphic analysis
B) flow chart
C) PERT diagram
D) quality control checkpoint
E) Gantt chart

Answer

This answer is hidden. It contains 1 characters.